Sherman Progress Park Sewer Contract Finalized
- Disclosed value
- $5,795,197.94
- From agendapacket
- Document date
- May 18, 2026
The 30-second brief
GTUA accepted Blackrock Construction's contract for the City of Sherman Progress Park Industrial Sewer Outfall Project as complete and approved a final Change Order No. 2, setting the total contract at $5,795,197.94.
Blackrock Construction holds this construction contract with Greater Texoma Utility Authority.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $5,795,197.94
- Document date
- May 18, 2026
- Vendor
- Blackrock Construction
- Source document
- Greater Texoma Utility Authority Agenda Packet 2026-05-18 (AgendaPacket)
Blackrock Construction's other public contracts
More Greater Texoma Utility Authority contracts
Questions about this contract
Who was awarded the construction contract by Greater Texoma Utility Authority?
Blackrock Construction was awarded this construction contract by Greater Texoma Utility Authority, as recorded on May 18, 2026. The contract value is $5,795,197.94.
How much is the Blackrock Construction contract with Greater Texoma Utility Authority worth?
The Blackrock Construction contract with Greater Texoma Utility Authority is valued at $5,795,197.94, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agendapacket record.
Where was this contract approved?
This contract appears in Greater Texoma Utility Authority Agenda Packet 2026-05-18 (AgendaPacket), dated May 18, 2026 from Greater Texoma Utility Authority. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 1 more question
What is Greater Texoma Utility Authority currently buying?
Explore Greater Texoma Utility Authority's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.