CONTRACTAMENDED

Board Approves Change Orders for Waterline Project

Gavilan College logoGavilan College
Disclosed value
Not to exceed net $190,920.20 (PCO 12 $30,298.86 + PCO 12a $127,525.24 + PCO 12b -$98,392.00 + PCO 14 $131,488.10)
From resolution
Document date
May 12, 2026

The 30-second brief

What it covers

The Gavilan Joint Community College District Board approved multiple change orders with Arizona Pipeline Company for Additional Work on the Domestic Waterline Project, with a combined not-to-exceed net increase of approximately $190,920.20. The Board found that formally rebidding this work would delay project completion and increase costs since the contractor is already mobilized.

Who holds it

Arizona Pipeline Company holds this construction contract with Gavilan College.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
Not to exceed net $190,920.20 (PCO 12 $30,298.86 + PCO 12a $127,525.24 + PCO 12b -$98,392.00 + PCO 14 $131,488.10)
Document date
May 12, 2026
Source document
Gavilan Joint Community College District Resolution Resolution Conveying Making Change Order Findings to Domestic Waterline Project 2026-05-12 (Resolution)

Arizona Pipeline Company's other public contracts

More Gavilan College contracts

Questions about this contract

Who was awarded the construction contract by Gavilan College?

Arizona Pipeline Company was awarded this construction contract by Gavilan College, as recorded on May 12, 2026. The contract value is Not to exceed net $190,920.20 (PCO 12 $30,298.86 + PCO 12a $127,525.24 + PCO 12b -$98,392.00 + PCO 14 $131,488.10).

How much is the Arizona Pipeline Company contract with Gavilan College worth?

The Arizona Pipeline Company contract with Gavilan College is valued at Not to exceed net $190,920.20 (PCO 12 $30,298.86 + PCO 12a $127,525.24 + PCO 12b -$98,392.00 + PCO 14 $131,488.10), covering construction work.

What type of contract is this?

This is a Construction contract, documented as a resolution record, structured as a not-to-exceed (ceiling) agreement.

Where was this contract approved?

This contract appears in Gavilan Joint Community College District Resolution Resolution Conveying Making Change Order Findings to Domestic Waterline Project 2026-05-12 (Resolution), dated May 12, 2026 from Gavilan College. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Arizona Pipeline Company hold?

Arizona Pipeline Company may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Gavilan College currently buying?

Explore Gavilan College's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →